Chapter 5 · Budget and schedule
37
Chapter 5 · ON CAFE worked example
Tool 5 ·
Schedule planning
ON CAFE's schedule: what must be ready to begin?
Before choosing dates, list what the next task needs. Once those conditions are understood, agree on targets with the responsible people. Document requests, initial pricing and design reviews may overlap.
| Task | When it can proceed | What must come first |
|---|---|---|
| Lease-term review Owner and lease reviewer | When answers and evidence for key conditions are available | Permitted use, delivery scope, cost responsibility and treatment of unknowns |
| Space delivery Landlord and owner | When contractual delivery conditions are met | Landlord work complete; access, keys and utility conditions satisfied |
| Equipment and design review Designer and owner | When the operating plan and equipment information are ready | Water-heater comparison, specifications, measurements and agency replies |
| Permits and formal pricing Designer and contractor | When reviewable drawings and work scope are available | Submittal conditions, review comments, quote inclusions and exclusions |
| Construction start Contractor | When required permits, contracts and site conditions are in place | Issued permits, construction contract, insurance and site access |
| Equipment delivery and installation Vendor and contractor | When access, storage and connections are ready | Orders, delivery route, power, plumbing and installation responsibilities |
| Inspections and opening preparation Authorities, contractor and owner | When inspections and corrections are complete and required approvals are issued | Applicable occupancy and health approvals, startup checks and staff training |
| Handover and early operation Owner and service providers | When equipment and facilities are handed over | Warranties, contacts, cleaning and inspection instructions, open-item records |
What else changes if a task slips?
A late oven specification can delay exhaust review and final pricing. A construction delay can affect equipment delivery, storage and rent exposure. Mark both the delayed task and the tasks it affects.
5
Tool 5 ·
Schedule planning
List each task, responsible person and prerequisite. Set target dates after replies arrive, distinguishing confirmed dates from desired ones.