C0 English edition 37 · ON CAFE's schedule: what must be ready to begin?

Chapter 5 · Budget and schedule

37

Chapter 5 · ON CAFE worked example

Tool 5 ·

Schedule planning

ON CAFE's schedule: what must be ready to begin?

Before choosing dates, list what the next task needs. Once those conditions are understood, agree on targets with the responsible people. Document requests, initial pricing and design reviews may overlap.

TaskWhen it can proceedWhat must come first
Lease-term review Owner and lease reviewerWhen answers and evidence for key conditions are availablePermitted use, delivery scope, cost responsibility and treatment of unknowns
Space delivery Landlord and ownerWhen contractual delivery conditions are metLandlord work complete; access, keys and utility conditions satisfied
Equipment and design review Designer and ownerWhen the operating plan and equipment information are readyWater-heater comparison, specifications, measurements and agency replies
Permits and formal pricing Designer and contractorWhen reviewable drawings and work scope are availableSubmittal conditions, review comments, quote inclusions and exclusions
Construction start ContractorWhen required permits, contracts and site conditions are in placeIssued permits, construction contract, insurance and site access
Equipment delivery and installation Vendor and contractorWhen access, storage and connections are readyOrders, delivery route, power, plumbing and installation responsibilities
Inspections and opening preparation Authorities, contractor and ownerWhen inspections and corrections are complete and required approvals are issuedApplicable occupancy and health approvals, startup checks and staff training
Handover and early operation Owner and service providersWhen equipment and facilities are handed overWarranties, contacts, cleaning and inspection instructions, open-item records

What else changes if a task slips?

A late oven specification can delay exhaust review and final pricing. A construction delay can affect equipment delivery, storage and rent exposure. Mark both the delayed task and the tasks it affects.

5

Tool 5 ·

Schedule planning

List each task, responsible person and prerequisite. Set target dates after replies arrive, distinguishing confirmed dates from desired ones.