Chapter 6 · Calculate the budget and the cash you need
58
Step by step
ON Seafood · Known and unknown prices
This table breaks down Site A’s site-comparison assumptions for the design stage. Separate a cost category from the items already inside it.
| Category | Amount | Included in / basis |
|---|---|---|
| Design agreement | $25,000 | Includes the $10,000 already paid |
| Additional structural review letter | $2,500 | Separate from the design agreement |
| Base construction | $220,000 | Planning assumption before bidding |
| Extra-work budget (owner-held) | $47,000 | Provisional; outside the base scope |
| Equipment package | $60,000 | Includes dishwasher supply, delivery and handling |
| Permit / filing fees | $6,000 | Agency confirmation pending; impact fees separate |
| Item 6 purchase / delivery | $10,250 | Detail within the $60,000 equipment category |
| Item 6 handling / placement | $600 | Within $60,000; final connections excluded |
| Hood suppression adjustment | $4,200 | Detail within the $47,000 extra-work category |
Do not add the detail twice
The $10,250 and $600 are already within $60,000, leaving $49,150 for other equipment. Removing the $4,200 suppression adjustment from $47,000 leaves $42,800 provisionally assigned to other extra work. Reconcile scope if a different contract includes the same cost.
The $2,500 structural review is a cost broken out after the initial site comparison. Dishwasher final connection and startup, grease-interceptor replacement and impact fees remain under review. This does not prove that $47,000 is sufficient. Check whether quotes include sales tax.