Chapter 3 · Check the scope of the document you received
28
Almost six more weeks of paperwork after the CO
FROM THE FIELD · A REAL PROJECT
This is a real project in Georgia, separate from ON Seafood. The dates below show this project’s sequence, not standard processing times. The document received on July 24 was a full CO, not a temporary CO.
Permitted Use
·
Activities allowed by the lease, read separately from government approvals.
Apr 12
Building permit / start
Construction began after permit issuance.
Jul 24
Completion / full CO
Applied for health inspection and city Zoning Verification.
Jul 31
Zoning approved
Zoning Verification completed.
Aug 2
Health / Life Safety passed
Passed the health inspection (Department of Public Health) and the Life Safety inspection (City Building Inspector).
Aug 13–14
County handoff / additional filing
Report handed off; a separate Commercial Building Permit was filed, starting water/sewer and backflow reviews.
Aug 27
Engineering review completed
Ten business days of review, then 1–2 days for the file to reach the city and 1–2 days for business license issuance.
Sep 2
Opened for business
The project installed its already-made sign after the business license was issued.
What this project teaches
• Forty days separated the CO and opening because paperwork and agency handoffs remained. • Early consultation and preparation did not eliminate processing time. • During construction, identify post-CO steps, parallel applications and the next contact; track each handoff.
Zoning Verification concerns permitted use; Life Safety Inspection concerns life-safety conditions. In this project, use verification, agency handoff and water and sewer review remained after the formal CO. An identically named procedure can play a different role elsewhere. The same City Building Inspector had already handled the fire inspection before the CO and came back for Life Safety after it.