Restaurant Design, Permits and Construction Preparation · 3 / 5

Restaurant Guide 2, page 58: ON Seafood · Known and unknown prices

Chapter 6 · Calculate the budget and the cash you need

58

Step by step

ON Seafood · Known and unknown prices

This table breaks down Site A’s site-comparison assumptions for the design stage. Separate a cost category from the items already inside it.

CategoryAmountIncluded in / basis
Design agreement$25,000Includes the $10,000 already paid
Additional structural review letter$2,500Separate from the design agreement
Base construction$220,000Planning assumption before bidding
Extra-work budget (owner-held)$47,000Provisional; outside the base scope
Equipment package$60,000Includes dishwasher supply, delivery and handling
Permit / filing fees$6,000Agency confirmation pending; impact fees separate
Item 6 purchase / delivery$10,250Detail within the $60,000 equipment category
Item 6 handling / placement$600Within $60,000; final connections excluded
Hood suppression adjustment$4,200Detail within the $47,000 extra-work category

Do not add the detail twice

The $10,250 and $600 are already within $60,000, leaving $49,150 for other equipment. Removing the $4,200 suppression adjustment from $47,000 leaves $42,800 provisionally assigned to other extra work. Reconcile scope if a different contract includes the same cost.

The $2,500 structural review is a cost broken out after the initial site comparison. Dishwasher final connection and startup, grease-interceptor replacement and impact fees remain under review. This does not prove that $47,000 is sufficient. Check whether quotes include sales tax.