Four places a low bid may leave a gap

Placement versus connection

“Set in place” means putting equipment in position; “final connection” means hooking it up to gas, power, water or waste lines. Ask separately about leveling, anchoring, startup and packaging removal.

Specialty work

Hood fire suppression, grease interceptor work, roof penetrations, waterproofing and low-voltage work may sit outside the GC’s quote. For each, note who performs the work, who holds the contract and who bills for it.

Costs surrounding the work

Locate permit, inspection and reinspection fees, landlord-required insurance or bonds, dumpsters and restricted-hours costs.

Restoration and final adjustment

Check wall repair and paint after piping and duct work, air balancing, final cleaning and restoration of existing surfaces. “Systems included” does not necessarily include finish restoration.

Put the response into the quote

Ask whether each missing line is included or separate. If included, have the bidder update the scope or quote. An omission is a question to resolve, not by itself proof of poor workmanship.

Companion workbook · Tool 2 | Bid comparison

Compare included, excluded and unverified items on a consistent scope.