Chapter 5 · Budget and schedule
34
Chapter 5 · ON CAFE worked example
Tool 4 ·
Budget planning
ON CAFE's startup costs and unknown amounts
All amounts below are teaching assumptions. "Unverified" does not mean $0. Review the subtotal of priced items, then investigate the costs still missing.
| Item | Example amount (USD) | Basis for the amount |
|---|---|---|
| Security deposit | $7,600 | Assumes two months of base rent |
| NNN charges | $4,500 | Assumes $900 per month for five pre-opening months |
| Base rent | $11,400 | Assumes $3,800 per month for three months after abatement |
| Design fee | $12,000 | Assumes $6,000 initial and $6,000 final payments |
| Permit fees | $2,500 | Placeholder for illustration |
| Change-of-use charges | Unverified | Awaiting the authority's reply |
| Base construction cost | $85,000 | Excludes additional systems and restroom work |
| Additional construction scope | Unverified | Electrical, grease control and restroom: provisional $20,000-$35,000 range |
| Equipment and fixture budget | $60,000 | Assumed total; recheck freight, connections and tax |
| Insurance premium | $1,500 | Placeholder; distinct from any insurance-certificate issuance fee |
| Signs | $4,000 | Placeholder |
| Accounts and other permits | $500 | Placeholder |
| Pre-opening operating funds | $25,000 | Assumes initial inventory, training and preparation costs |
| TI reimbursement | Unverified | 1,200 sq ft × $15 = $18,000. Verbal proposal; awaiting written terms |
Subtotal of priced items: $214,000
This assumed subtotal combines $189,000 in pre-opening cash outlays, including the deposit, with $25,000 in operating funds. The deposit's accounting treatment and return conditions are separate. Unknown costs and additional reserves remain, so this is neither a final total budget nor a maximum funding requirement.