Chapter 5 · Budget and schedule

34

Chapter 5 · ON CAFE worked example

Tool 4 ·

Budget planning

ON CAFE's startup costs and unknown amounts

All amounts below are teaching assumptions. "Unverified" does not mean $0. Review the subtotal of priced items, then investigate the costs still missing.

ItemExample amount (USD)Basis for the amount
Security deposit$7,600Assumes two months of base rent
NNN charges$4,500Assumes $900 per month for five pre-opening months
Base rent$11,400Assumes $3,800 per month for three months after abatement
Design fee$12,000Assumes $6,000 initial and $6,000 final payments
Permit fees$2,500Placeholder for illustration
Change-of-use chargesUnverifiedAwaiting the authority's reply
Base construction cost$85,000Excludes additional systems and restroom work
Additional construction scopeUnverifiedElectrical, grease control and restroom: provisional $20,000-$35,000 range
Equipment and fixture budget$60,000Assumed total; recheck freight, connections and tax
Insurance premium$1,500Placeholder; distinct from any insurance-certificate issuance fee
Signs$4,000Placeholder
Accounts and other permits$500Placeholder
Pre-opening operating funds$25,000Assumes initial inventory, training and preparation costs
TI reimbursementUnverified1,200 sq ft × $15 = $18,000. Verbal proposal; awaiting written terms

Subtotal of priced items: $214,000

This assumed subtotal combines $189,000 in pre-opening cash outlays, including the deposit, with $25,000 in operating funds. The deposit's accounting treatment and return conditions are separate. Unknown costs and additional reserves remain, so this is neither a final total budget nor a maximum funding requirement.