Confirm what goes to each authority
Ask your designer to explain the decisions you must make and each agency's submission process, rather than trying to interpret all the drawings alone.
| What to prepare | Responsible person | Evidence to keep |
|---|---|---|
| Planning, building, health, fire and sewer review routes | Designer | Application and review list by authority |
| Change of use and possible additional charges | Designer and relevant authority | Replies on the current plan and costs to verify |
| Equipment and system conditions shown in drawings | Owner and designer | Matched requirements, gaps and information still needed |
| Menu, seating, equipment and kitchen layout | Designer and health department | Required health-review submittals |
| Hood suppression, sprinklers and related systems | Designer and fire authority | Whether separate submissions or vendor design are required |
| Grease control and drainage | Designer and sewer authority | Written new-installation, replacement or retention requirements |
| Landlord drawing approval, if required by the lease | Owner and landlord | Written approval scope and conditions |
| Agency submission and expected review timing | Designer | Tracking number, drawing date/revision and next follow-up date |
When given a duration, also ask what could delay it.
In practice · Field experience
A building where design took six months
A narrow duct shaft in a new commercial building required additional design and structural review. At this site, drawings took six months and construction then took 16 months.
Your next action
Ask about recent projects with similar local conditions and work scope. Check how unresolved routes and your decisions may affect this project's schedule.
Reconstructed from field experience for teaching. Image is an explanatory illustration.