If the new counter replaces a cabinet, where is the credit?

Show added and removed work in the same change record. Separate proposed amounts from approvals, and track the net price and schedule effect.

4 min read · Build · By Open Note USA Editorial Team

A restaurant service counter and surrounding space for a scope-change discussion
AI-generated image for illustration.

The short note

You change the counter plan during construction and receive a $12,000 addition. But the new counter also replaces a separate storage cabinet originally in the contract. The added and removed work both matter to the price of this change.

What to check

  • Original scope: mark where the removed item appears in the contract or quote. Removing something never included does not create a credit.
  • Additions and credits: give each scope item its own line. Ask about overlapping labor or material charges and use the same tax and fee basis.
  • Work already committed: identify orders, fabrication, completed work and cancellation or return conditions. Removed scope does not automatically produce a full refund.
  • Approval and time: distinguish a quote, an open negotiation and an approved change. Follow your contract’s approval process and record lead-time or completion effects.

Why it matters

Using the video’s illustrative figures, a $12,000 addition less an agreed $3,000 credit produces a $9,000 net increase. If $3,000 is only a request, do not treat $9,000 as approved. Keep the proposed addition and requested credit separate until agreement.

AIA’s change-order guidance describes documenting agreement on changes to work, contract price and time. That does not make a particular AIA form mandatory for every job. Use your actual contract’s process.

Reference: AIA Contract Documents — fundamentals of change orders

Questions to ask

Ask the construction lead and change approver

  • Which original contract items will no longer be performed because of this change?
  • What materials, labor and cancellation terms support the proposed credit?
  • Can the change record show the net adjustment, tax/fee basis and schedule effect together?

Your next step

Cross-reference the original cabinet line on the change order. Keep the proposed addition, requested credit and approved net change separate. When the next invoice arrives, match the change number and check that the approved amount appears once. Follow the contract’s notice procedure for disputed items.

Version v1.1 · Published 2026-10-11 · Last reviewed 2026-11-06

Tell us what was unclear or what you need nextShare feedback

One short suggestion is enough. Prepare your message below, then review and send it in your email app.

Please leave out personal details, order numbers and private download links. This page does not send or store your entries on a server.

hello@opennoteusa.com · Privacy policy

Find my next step

1 / 3

Answer three questions and we'll point you to resources and first steps that fit where you are.

What kind of space are you preparing?