The short note
The contractor has started. Can you wait until just before opening to visit? Even with professional construction management, equipment selections and operating preferences may still need your answer. Knowing when your decision is needed is a useful owner responsibility.
What to check
- One point of contact: send questions and changes through the construction lead. Avoid giving separate directions to trades.
- Checkpoints and format: agree when a visit, photos or a call is useful for the work ahead. Arrange safe site access with the crew.
- Prerequisites for upcoming work: ask what happens next and which model, finish or location decisions you must confirm beforehand.
- Decision record: retain the date, location, question, responder and needed-by date. Follow the agreed change process for scope, price and time impacts.
Why it matters
Suppose the team asks about countertop outlet locations. Sending the actual equipment list is more useful than “put them wherever you think.” The owner explains intended use; the design and construction team evaluates suitable locations and technical requirements.
An owner check-in is different from a regulatory inspection. You are not certifying plumbing or electrical work. Learn the team’s inspection and work schedule, then supply owner decisions in time for that schedule.
Questions to ask
Ask the construction lead
- What should be complete by our next check-in, and what starts after that?
- Which decisions do you need from me, and by when?
- Who will document the scope, price and schedule effects of the change we discussed?
Your next step
Before the next visit, ask the construction lead which decision they need from you. If you discuss moving something on site, record it as a request for review. Check the cost and schedule impact before approving it through the agreed process.